Before proceeding with the physical installation of the chain system, it is essential to prepare the power supply connections.
The primary connection involves supplying power to the master unit. Use a 230V-50Hz power source (or 110V-60Hz for installations in regions using the US power grid).
Connection terminals are clearly labeled on the diagram:
F – Phase
N – Neutral
Ground – Marked with the standard ground symbol
You can see the image of the Parklio Chain power supply to master unit connectors at the following link: https://file.parklio.co/file/pawnaf1a5e5c237ef4050ad6f634fddf45604
The slave unit contains only the motor and operates in sync with the motor in the master unit. To enable this simultaneous operation, you must connect the terminals marked + and - for Motor 2 on the master unit to the corresponding + and - terminals on Motor 2 in the slave unit.
Refer to the provided diagram for the exact position of the Motor 2 connections in the master unit.
The cross-section of the cables used for connecting Motor 2 depends on the distance between the master and slave units:
Up to 5 meters: Use cables with a minimum cross-section of 1.5 mm²
From 5 to 18 meters: Use cables with a minimum of 2.5 mm²
For long distances (18–20 meters): Use cables with a cross-section of at least 5 mm²
Recommendation: For optimal performance and simplified installation, we recommend using 2.5 mm² cables for all distances except for long-distance connections (above 18 meters), where 5 mm² cables should be used.
Ensure all cables are suitable for outdoor use and comply with local electrical codes and safety standards.